Skip to main content

DECREE 69/2024 so-called “Decreto Salva Casa”

In force from 30 May 2024

THE OBJECTIVES

The decree stems from the need to introduce simplification measures in the fields of construction and urban planning to overcome interpretative uncertainties and enable the redevelopment and economic enhancement of buildings and housing units.

Among the primary objectives of the decree is the revitalisation of the property sales market to meet the growing housing demand while supporting goals to reduce land consumption and encourage urban regeneration and the reuse of developed land.

THE KEY CHANGES IN BRIEF:

SIMPLIFIED REGULARISATION

For works carried out with partial discrepancies compared to the titles filed with the local authority, the requirement for double compliance is removed: to regularise, it is sufficient for the intervention to comply with the technical regulations in force at the time of execution. The issuance of the permit and the retrospective SCIA is subject to the payment of a fine ranging from €1,032 to €30,984, with approval by silence-assent after 45 days. Legislation for total unauthorised developments remains unchanged.

LEGAL STATUS

It is no longer necessary to reconstruct the entire chain of titles on file; the last title alone is sufficient: if the local authority did not contest irregularities in the past, it can no longer do so.

PERMITTED DEVELOPMENT

The list of interventions allowed as permitted development has been expanded. Included, for example, are all “sun and weather protection works whose main structure consists of awnings […] that are attached or annexed to buildings or housing units, even with fixed structures necessary for support and extension,” as well as the construction of porticoes without requiring specific authorisations.

CHANGE OF USE WITHOUT WORKS

Changes of use are allowed without the need for works, for example from industrial to residential, particularly within urban areas, “while maintaining the option for municipal planning tools to set specific conditions.” Furthermore, such changes are not subject to the obligation to secure additional general interest areas (as per Ministerial Decree 1444/68) or the constraint of minimum parking space provisions (Law 1150/42).

CONSTRUCTION TOLERANCES

For works completed by 24 May 2024, the limit for construction tolerances – i.e., the deviation between what was filed with the local authority and what was realised – has been increased from the current 2%. This percentage will vary between 2% and 5% proportionally to the surface areas of the properties:

  • 2% for housing units with a usable surface area exceeding 500 sq m;
  • 3% for housing units with a usable surface area between 300 and 500 sq m;
  • 4% for housing units with a usable surface area between 100 and 300 sq m;
  • 5% for housing units with a usable surface area below 100 sq m.

EXECUTION TOLERANCES

For works completed by 24 May 2024, execution tolerances include:

  • a smaller building size;
  • the non-realisation of non-structural architectural elements;
  • execution irregularities of external and internal walls;
  • the differing execution of works falling under ordinary maintenance;
  • design errors corrected on-site;
  • material errors in the project representation of works. REGULARISATION WITHOUT PENALTIES FOR PUBLIC ADMINISTRATIONS. The measures on tolerances and the new regularisation for partial discrepancies will also apply to public administration activities, which will, however, be exempt from paying fines.

POTENTIAL DEVELOPMENTS

Various proposals and comments have been made regarding the new provisions, particularly concerning construction and execution tolerances, for which stakeholders have requested the removal of temporal constraints.

Despite the simplifications introduced and the extensions requested, which are intended to provide greater certainty and facilitate both construction interventions and property sales, the actual impact of these measures on the property market remains unclear.

Leave a Reply